TUESDAY,
FEBRUARY 7, 2006, 5 P.M.
WORKSHOP
MEETING
Chairman
Millard called the workshop to order at 5 p.m.
Stephen
L. Millard, Chairman
Donald
L. Steinmeier, Vice Chairman
Kenneth
L. Tyndale, Secretary/Treasurer
William
LaDieu
Robert
R. Jones
Jon
A. Yost, Authority Solicitor
Dale
C. Shope, Authority Engineer
William
Smyers, Gannett Fleming
Mark
A. Salisbury, Authority Manager
Philip
G. Rodemoyer, Assistant Superintendent
Gail
A. Martin, Administrative Assistant
Mr. Millard called the members’
attention to the memorandum from Township Manager Michael Rimer regarding the
Millstone Settlement Agreement. The
Board of Supervisors approved the agreement contingent upon any final comments
by the Authority regarding remedies related to the development and fill around
Authority sewer lines and easements.
Mr. Millard indicated that no
provisions were made in the Agreement to rectify the problems created around
the Authority’s easement in Millstone Phase I.
A brief discussion followed.
Mr. Jones moved, seconded by Mr. Tyndale, to authorize the Authority’s engineer to include any corrections to the Agreement needed in order to resolve the Phase I easement issue. The motion was unanimously approved.
Mr. Millard indicated that he and Mr.
Jones had spent a considerable amount of time researching construction and
screen alternatives in order to cut the costs of moving the influent screen to
a location near the SBR tanks, which was previously estimated at $900,000.
Mr. Millard reported that he and Mr.
Jones had come up with a possible alternative, which would cost approximately
$100,000, including the building, two screens manufactured by IPEX, and a
compactor. A lengthy discussion ensued,
during which several alternative suggestions were offered regarding the screen
manufacturer that could be used. One of
the suggested alternatives was an influent screen manufactured by Rotomat. Mr. Shope indicated that members of the
Authority might want to consider visiting
Mr. Shope also
indicated that Gannett Fleming had engineered a Rotomat screen at the treatment
facility located in
Discussion was also held regarding
replacement of the raw wastewater pumps.
The estimate prepared by the Authority’s engineer for the influent
screen also included purchasing three new raw wastewater pumps at a cost of
approximately $83,000.
Mr. Salisbury indicated that the pumps were rated for 900 gpm but
that currently they were only pumping between 300-400 gpm. Up to this point, staff has been unable to
pinpoint whether or not there were any specific problems with the pumps. Mr. LaDieu suggested that perhaps there was a
blockage located in the lines and that the pumps were not functioning properly
due to that blockage. He recommended
that a gauge should be installed on the force main to measure the static and
pumping head pressures. Staff was
directed to proceed with that recommendation and report back to the Authority.
A question was raised regarding
whether or not a building could be constructed that was not explosion proof in
order to contain costs. Mr. Shope
responded by saying that the building he proposed did not have to be explosion
proof because all of the mechanical and electric components were contained away
from the actual wastewater coming into the building. Those items would be contained in their own
room.
Mr. Millard
stated that he and Mr. Jones had some concerns regarding the estimated
engineering costs for the influent screen, which were estimated at
$69,000. He indicated that he believed
those costs to be out of line. Mr. Shope
reviewed the memorandum he had provided for the Authority’s meeting on January
24.
Mr. LaDieu
pointed out that the Authority would most likely incur significant engineering
fees associated with preparing a land development plan for the screen project
as well as the vermicomposting project.
He indicated that he believed there might be some issues related to
stormwater management and/or impervious surface restrictions. Mr. Millard indicated that the Township
agreed to waive the fees associated with a land development plan but would not
waive preparation of such a plan. A
lengthy discussion followed, during which it was suggested that the Authority
prepare a sketch land development plan combining both projects into one
submission. It was agreed that the
preliminary plan should include the influent screen facility as well as the
entire vermicomposting plan, which would include approval of a building to
house 20 worm beds, with Phase I being construction to house 12 worm beds.
Mr. Jones
moved, seconded by Mr. Tyndale, to authorize Gannett Fleming to prepare a
sketch plan in order to meet with Township personnel to identify any land
development or zoning issues.
At the conclusion of the discussions,
by consensus, the Authority agreed to the following recommendations:
· The influent screen should be relocated near the SBR tanks.
· Staff should verify the condition of the pumps.
· Authority members and/or staff should view the Rotomat pumps
used by the wastewater treatment plant in
· A conventional building (e.g., block walls) should be
considered to house the influent screen.
Mr. Millard reported that he and
other members of the Authority had spent considerable time researching some
possible alternatives for the vermicomposting facility in order to cut the
proposed costs of $1.2 million.
Mr. Jones distributed folders from
Dueck Construction providing information on a building alternative to
steel. Marvin Dueck of Dueck
Construction arrived shortly after with a drawing of a proposed building. The cost of the building was projected at
approximately $300,000-$333,000 and did not include electric, plumbing,
excavation, ventilation, or cooling systems. This building included
construction with wood versus steel construction. A brief discussion followed, after which the
members thanked Mr. Dueck for coming to the workshop.
Mr. Tyndale called the members’
attention to samples of building materials that he has used in the construction
of car washes. The building would be
manufactured in 8-foot sections using a type of recycled plastic. The building is then brought from the factory
in sections and constructed with minimal labor costs. He stated that he asked
Following further discussion, the
Authority members agreed with the following recommendations:
· Staff should contact the Authority’s insurance carrier to
determine whether the costs could increase significantly if wood were used in
the construction of the building versus steel.
· The height inside the building should be a minimum of 16
feet.
· Consideration should be given to installing some type of
louvers and/or fans to assist in reducing heating and cooling costs.
· Cost estimates should be obtained showing construction of a
building using steel, Superior Walls, and recycled plastic.
· Following review of the estimates, the Authority should make
a decision regarding construction material and outline the specific materials
and/or name-brand products to be used in the bidding process.
· It was agreed that this project needed to move forward, as
the vermicomposting equipment was due to be delivered in May or June 2006.
Mr. LaDieu moved, seconded by
Mr. Tyndale, to adjourn the workshop.
The motion was unanimously approved. The workshop adjourned at 8:30 p.m.
Respectfully
submitted,
Gail
A. Martin,
Recording
Secretary