WEST HANOVER TOWNSHIP WATER & SEWER AUTHORITY

7901 JONESTOWN ROAD, HARRISBURG, PA  17112

TUESDAY, SEPTEMBER 18, 2007, 6 P.M.

REGULAR MEETING

 

 

CALL TO ORDER

 

        Chairman Millard called the regular meeting to order at 6:03 p.m., followed by the Pledge of Allegiance.

 

ATTENDANCE

 

        Stephen L. Millard, Chairman

        Donald L. Steinmeier, Vice Chairman

        Kenneth L. Tyndale, Secretary/Treasurer

        Robert R. Jones

 

PUBLIC COMMENT

       

        No public comment was offered at this time.

 

PRESENTATION

 

        S&A Homes.  Justin Kuhn of K&W engineers, representing S&A Homes, was present to discuss the proposed Oak Grove Manor development to be located along the northwest side of the Oak Grove Road/Sterling Road intersection.  The property is owned by the Catholic Diocese, with S&A Homes being the builder interested in developing the property.

        Mr. Kuhn reviewed his letter dated September 13, 2007, with included the two following two options for providing public sewer service to the development.

        Option 1 would convey the flow from Oak Grove Manor to Pump Station #5.  This option would include installing a new pump station (80 gpm) that would collect and convey sanitary sewer from the site to existing Pump Station #5.  Pump Station #5 would need to be upgraded to handle the increase flow.  The cost of Option 1 would be $361,826, which would be funded entirely by the developer.

        Option 2 would convey flows from the Oak Grove Manor development, Pump Station #10, and Pump Station #5 to a relief force main along the north side of Allentown Boulevard.  This option would include the installation of a new pump station (400 gpm), with abandonment of Pump Station #10 and Pump Station #5.  Gravity sewers would be installed from Pump Station #10 and Pump Station #5 to Oak Grove Manor, at a cost of $582,936.  

        Mr. Kuhn stated that it was his understanding that the Authority would prefer Option 2 to allow the Authority to (1) decrease the overall number of pump stations within the Township and (2) relieve pending capacity issues facing Pump Station #6.  The increased cost of Option 2 over Option 1 would be $221,110.  Mr. Kuhn added that S&A Homes would be willing to construct the necessary improvements to implement Option 2, if the Authority would be willing to provide reimbursement for the net difference via reduced tapping fees, inspection fees, etc.

        A lengthy discussion followed Mr. Kuhn’s presentation.  By consensus, the Authority agreed to have the Authority’s engineer look at the issues and discuss this project at a future meeting.

        Mr. Kuhn thanked the Authority for their time.

 

 

APPROVAL OF MINUTES

 

        Regular Meeting, August 21, 2007.  Mr. Steinmeier moved, seconded by Mr. Jones, to approve the August 21, 2007 Minutes as distributed.  The motion was approved 3-0, with Mr. Tyndale abstaining as he was not present at that meeting.

 

FINANCIAL REPORTS

                                                                                                                  

        Operating Expenses.  Mrs. Martin reported that prepaid invoices totaled $39,781.54.  Mrs. Martin also reported that invoices pending payment totaled $224,641.12. 

        Mr. Jones moved, seconded by Mr. Steinmeier, to approve the prepaid invoices in the amount of $39,781.54.  The motion was unanimously approved.

        Mr. Jones moved, seconded by Mr. Tyndale, to approve the pending invoices in the amount of $224,641.12.  The motion was unanimously approved.

        The Authority briefly reviewed the arrears listing and directed Mr. Yost to write letters to those residents in arrears more than $300.

 

OLD BUSINESS

 

        Update on Vermitech.  Mr. Salisbury reported that the building was scheduled for substantial completion in December 2007.  He added that worms are being cultivated at the plant in preparation for operation of the vermicomposting process by January 2008. 

        Mr. Salisbury called the Authority’s attention to a letter dated September 14, 2007 from Shaun Ankers of Vermitech USA, Inc., requesting another installment payment in the amount of $146,250 to offset ongoing costs being incurred by Vermitech in light of the unfortunate delay in the project.  A lengthy discussion followed, during which it was suggested that Mr. Salisbury should review the contract to determine the payment schedule and report back at the October meeting.

        Mr. Tyndale moved, seconded by Mr. Steinmeier, to table the request for payment until the October 2007 meeting.  The motion was unanimously approved.

        Mr. Millard expressed some concern over the amount of cracking on the floor of the building.  Mr. Tyndale stated that he also believed that there were more cracks than he would like to see.  Following a brief discussion, it was agreed that the Authority’s engineer should request a written opinion regarding the stability of the concrete.  Mr. Shope agreed to provide a report to the Authority at the October meeting.

 

        Update on Swatara Capacity.  Mr. Millard reported that he attended a meeting at the Swatara treatment plant on September 12, 2007.  A presentation was made showing the costs that would be incurred in upgrading the treatment plant.  Mr. Millard called the members’ attention to the breakdown of costs, which total $15,173,250.  West Hanover Township would be required to pay approximately $1.3 million toward the upgrades.  Mr. Millard also reported that the upgrades would be completed by 2010.  He stated that a representative from the Swatara Authority would be in contact with the Authority’s engineer to discuss the upgrades.  A lengthy discussion followed.

        Mr. Yost reported that discovery continues in the arbitration case.

 

        Update on Influent Screen at the Treatment Plant.  TABLED.

 

        Evergreen Ridge (Currently tabled at the Township).  TABLED.

 

        Repair/Replace Utility Pole on Authority Property.  Mr. Tyndale reported that he would meet with Mr. Salisbury during the week of September 24.

 

        Reduction of Escrow Funds/Deed of Dedication for Country Hearth.  Mr. Yost reported that this matter remained unresolved but added that he would do his best to complete it for the October 2007 meeting.

 

        Summit Family Restaurant/Generator for Pump Station #1.  Mr. Shope called the members’ attention to his memorandum dated September 18, 2007.  Mr. Shope briefly reviewed the memorandum, with the final conclusion being that since Pump Station #1 could not be eliminated by constructing a gravity sewer, and given that the costs associated with the construction of a new gravity sewer are prohibitive at approximately $80,000.  Mr. Shope made a recommendation that the Summit Family Restaurant and the Sleep Inn proposed for Harper Drive be permitted to connect to the existing sewer system tributary to Pump Station #1.  However, both developers would be required to contribute toward the installation of a generator.  The costs to install a generator would be approximately $48,600.

 

        Proposed Changes to Requirements for Developers to Pay to Update GIS Mapping.  The following changes were recommended to the Sewer Extension and Security Agreement:

        To Paragraph 5.a., ad after the word “thereof” the following:  “and one (1) digitized plan set in a format approved by the Authority; and”

        To Paragraph 9, add the following new sub paragraph:  “e. The reasonable charges for updating the Sewer Index Map of the Authority’s Sanitary Sewer System to add the new extension.”

        Mr. Tyndale moved, seconded by Mr. Jones, to adopt the recommended changes to the Sewer Extension and Security Agreement.  The motion was unanimously approved.

 

NEW BUSINESS

 

        Insurance for Authority.  Mr. Salisbury reported that Erik Olsen from Strickler Insurance visited the treatment plant and pump stations to obtain some of the information he needed to provide a quote for insurance.  Mr. Olsen also contacted Township Manager Mike Rimer to obtain some additional information, which has not yet been received.

 

        7624 and 7652 Green Hill Road.  Mr. Salisbury called the members’ attention to his memorandum dated September 7, 2007.  Mr. Salisbury raised the question as to whether or not the Authority wanted to install laterals for these two properties off manholes installed in the Sagewicke Phase IV and Annex cul-de-sacs.  If the laterals were installed, both properties would be within 150 feet of the public sewer line.  A brief discussion followed.

        Mr. Tyndale moved, seconded by Mr. Steinmeier, that the properties located at 7624 and 7652 Green Hill Road should not be required to connect to the public sewer system at the present time.  The motion was unanimously approved.

 

        Jason Weiser.  Mr. Salisbury called the members’ attention to Mr. Shope’s letter dated August 27, 2007 regarding the proposed three-lot subdivision proposed for property owned by Jason Weiser.  Mr. Weiser’s plan calls for construction of a low-pressure force main to serve this subdivision.  Mr. Salisbury raised a question as to whether the Authority should require Mr. Weiser to construct a gravity sewer line to serve the proposed subdivision.  It was pointed out that if a gravity sewer line was required, the cost to the developer would be substantially more than the proposed low-pressure force main and that the developer would likely look to the Authority for some cost sharing.  Mr. Salisbury added that the letter was provided for information only at the present time.

 

PUBLIC COMMENT

 

        No public comment was offered at this time.

 

CORRESPONDENCE

 

        Mr. Salisbury briefly reviewed the correspondence included with the packets.

 

AUTHORITY MEMBER COMMENTS

 

        Bob Jones.  Mr. Jones stated that he believed it was important to schedule a meeting between the Authority and the Board of Supervisors to discuss the Swatara capacity.  He asked Mr. Salisbury to work on scheduling a workshop meeting following the election in November in order that the two new supervisors could be included.

 

        Ken Tyndale.  Mr. Tyndale had no comments.

 

        Steve Millard.  Mr. Millard had no comments.

 

        Don Steinmeier.  Mr. Steinmeier had no comments.

 

REPORTS

 

        Authority Manager.  Mr. Salisbury submitted a written report.  In addition, he called the members’ attention a proposal from Aqua-Aerobic Systems, Inc. for replacement of the bubble diffusers in the amount of $103,196.  Mr. Salisbury also called the members’ attention to a proposal in the amount of $43,540 from Tesco Controls, Inc. for replacement of the raw water pumping station control panel at the treatment plant.

 

        Authority Engineer.  Mr. Shope submitted a written report. 

 

        Authority Solicitor.  Mr. Yost had no further report.

 

ADJOURNMENT

 

        Mr. Jones moved, seconded by Mr. Tyndale, to adjourn the meeting.  The motion was unanimously approved.  The meeting adjourned at 8:18 p.m.

 

                                                                                      Respectfully submitted,

 

                                                                                      Gail A. Martin

                                                                                      Recording Secretary