IN THE MATTER OF THE : WEST HANOVER TOWNSHIP
APPLICATION OF : ZONING HEARING BOARD
CENTRAL DAUPHIN SCHOOL :
DISTRICT : DOCKET NO. 2002.08
DECISION GRANTING SPECIAL EXCEPTION
TO
PERMIT CONSTRUCTION OF PUBLIC
FACILITIES AND IMPROVEMENTS
WITHIN FLOODPLAIN AND GRANTING
VARIANCES FROM REQUIREMENTS
OF CERTAIN ENVIRONMENTAL PROTECTION
OVERLAY DISTRICTS
Applicant
has requested a special exception to permit construction of public facilities
within a floodplain and also has requested variances from certain of the
environmental protection overlay districts of the West Hanover Township Zoning
Ordinance to permit construction of a high school, athletic fields, and related
facilities.
FINDINGS
OF FACT
1. The Applicant is Central Dauphin School
District of 600 Rutherford Road, Harrisburg, Pennsylvania 17109.
2. Applicant is the owner of the subject
property pursuant to a Declaration of Taking filed on June 29, 2001 entered to
Docket Number 3035-S-2001 of the Dauphin County Court of Common Pleas. A copy of the Declaration of Taking was
admitted into evidence as Applicant’s Exhibit Number 1.
3. The subject property consists of nearly
100 acres and is zoned Flexible Rural Agriculture (FRA) and partly Rural
Residential (RR). The property is
located at the southeast quadrant of the intersection of Linglestown Road and
Piketown Road.
4. The Tax Parcel Number for the subject
property is 68-022-001.
5. Applicant received conditional use
approval from the Supervisors of West Hanover Township, as confirmed in a
letter dated January 22, 2002. A copy
of the January 22, 2002 letter was admitted into evidence as Applicant’s
Exhibit Number 2.
6. Gary Bannon, a registered, licensed
architect with E.I. Associates testified on behalf of Applicant as an expert in
design and construction of school projects.
7. Mr. Bannon’s Curriculum Vitae was
admitted into evidence as Applicant’s Exhibit Number 3.
8. Mr. Bannon testified as to the use and
design of the property for a high school building, athletic fields and related
facilities.
9. Admitted into evidence as Applicant’s
Exhibit Number 4 was the Special Exception Plan which shows the existing
features and improvements on the subject property, including Beaver Creek along
the western property line of the property, current improvements including a
house, outbuildings and a pond accessed over a private road.
10. Mr. Bannon testified that the Applicant
intends to keep the existing facilities and may use them for an environmental
center.
11. Mr. Bannon testified that Piketown Road
will be realigned at its intersection with Route 39 to meet concerns of West
Hanover Township, Lower Paxton Township, the Pennsylvania State Police, and the
Pennsylvania Department of Transportation regarding the safety of that
intersection.
12. Current Piketown Road is subject to
flooding and Mr. Bannon testified that the realignment project will involve
elevating the road which will decrease the flooding. In connection with that realignment a stream crossing will also
be eliminated.
13. Mr. Bannon identified wetland areas on
the plan which are marked in blue which will be impacted by the realignment of
Piketown Road.
14. Mr. Bannon testified that the realignment
of Piketown Road will have no impact on water or sewer facilities in the area
and will not affect neighboring property owners.
15. Mr. Bannon then discussed the variance
plan, which was admitted into evidence as Applicant’s Exhibit Number 5.
16. That plan shows environmental protection
overlay districts containing the acreage as follows:
Slope
Protection Overlay District (SPOD) 4.77
acres
Hillside
and Slope Protection Overlay District (HSPOD) 1.93
acres
Lake
and Pond Protection Overlay District (LPPOD) 2.51
acres
Wetland
Protection Overlay District (WPOD) 16.76
acres
1. Of those environmental protection
overlay districts, only the colored areas as depicted on Applicant’s Exhibit
Number 5 will be impacted by the construction.
2. The most significant impact on the
environmental protection overlay districts result from the realignment of
Piketown Road.
3. Mr. Bannon testified that
environmentally, relocating Piketown Road is better because it removes an
existing road and stream crossing and all wetland areas will be contiguous and
west of Piketown Road.
4. Mr. Bannon testified that the athletic
fields at the southern portion of the property are necessary to have the
minimum requirements for high school use, and if fields are not located there,
students would have to be bused elsewhere for athletics.
5. Mr. Bannon testified that there will be
no competition football field/stadium constructed on the property.
6. Jeffrey Staub, a registered
professional engineer since 1982 testified on behalf of Applicant. His Curriculum Vitae was admitted into
evidence as Applicant’s Exhibit Number 6.
7. Mr. Staub identified Applicant’s
Exhibit Number 7 which is a Memorandum concerning the acreages of the various
environmental protection overlay districts impacted by the proposed project.
8. Of the 4.77 acres within the SPOD, only
.75 acres are impacted and that is by the realignment of Piketown Road.
9. Mr. Staub also testified that of the
1.93 acres within the HSPOD, 1.49 acres are impacted.
10. There are no affected portions of the
2.51 acres covered by the LPPOD.
11. Of the 16.76 acres within the WPOD, Mr.
Staub testified only 4.55 acres are impacted.
12. Mr. Staub concluded his analysis of
impacted acres indicating that of the 10.79 acres in the wetlands, only 2.49
acres are impacted.
13. Mr. Staub identified Applicant’s Exhibit
Number 4 as being a document prepared by him concerning the floodplain.
14. Only 1.40 acres are in the floodplain and
the impact on the floodplain results solely from the realignment of Piketown
Road and the widening of Piketown Road in accordance with Township
requirements.
15. Mr. Staub testified that Piketown Road
could not be realigned without impacting the environmental protection overlay
districts.
16. Mr. Staub testified that not all of the
hydraulic studies are completed with regard to calculations of the 100 year
floodplain, however, he doubts that there will be an increase in the flood
height because in total there will be less fill in the floodplains after
realignment of Piketown Road than currently exists.
17. In any event, with regard to the
realignment of Piketown Road, Mr. Staub testified that the design will be
modified, if needed, to guarantee a zero increase in the flood heights and a
zero increase in flood velocities of Beaver Creek.
18. Mr. Staub testified that in his opinion
there might be a slight decrease in the 100 year flood height upstream north of
Route 39, and that there definitely will not be an increase in the 100 year
flood height upstream.
19. Mr. Staub testified that wetland
mitigation would occur in the area where the bridge currently crosses Beaver
Creek, which will be removed in connection with realignment of Piketown Road.
20. Edward Van Blargan, a professional
engineer who has conducted approximately 500 wetland delineation studies,
testified on behalf of Applicant. His
Curriculum Vitae was admitted into evidence as Applicant’s Exhibit Number 8.
21. Mr. Van Blargan did a wetlands delineation
study on the site and flagged the wetland areas.
22. He testified that wetlands are identified
by hydric soils, wetland plant community, and visible wetland hydrology.
23. Mr. Van Blargan identified the WPOD areas
on Applicant’s Exhibit Number 5 which contain the wetlands.
24. Mr. Van Blargan testified that the
wetlands along the southern boundary of the property have been mowed for hay
and it is, therefore, difficult to delineate and at best, on a scale of one to
ten, with one being the lowest quality wetland area, the areas along the
southern boundary are rated one.
25. Mr. Van Blargan testified that filling in
of wetland areas at the southern portion of the property will have no greater
environmental adverse effect than developing an upland area.
26. Mr. Van Blargan testified that the
wetlands along the western boundary of the property area are a higher quality
and would rate them approximately a four and a half on a scale of one to ten.
27. If the special exception and variance
were granted, Mr. Van Blargan testified that wetlands mitigation would have to
be completed to the requirements and satisfaction of PADEP and the Army Corps
of Engineers.
28. Although a specific plan is not yet
developed, Mr. Van Blargan testified that the Applicant does not intend to pay
into a fund and that it would probably do a combination of mitigation around
the stream, the back of the pond and perhaps at the southwest corner of the
property where the road is to be removed along the stream.
29. Applicant agreed to provide one to one
onsite wetlands mitigation for officially identified wetland areas, and that it
would do the wetlands mitigation in areas adjacent to existing wetlands.
30. Admitted into evidence as Applicant’s Exhibit
Number 9 was a transcript from the conditional use hearing which addresses many
of the variance criteria.
31. The Township’s representative testified
that relocation of Piketown Road is desirable from the Township’s perspective
and it supports the relief necessary to accomplish that realignment project.
32. The Applicant agreed with the following
conditions if the special exception and variances were granted:
(a) To provide one to one onsite wetlands
mitigation of officially delineated wetland areas adjacent to existing
wetlands;
(b) That there will be no increase in the
flood height of Beaver Creek;
(c) That there will be no increase in the
flood velocity of Beaver Creek;
(d) That any disturbed HSPOD areas will be
leveled and not permitted to erode; and
(e) Approval of a Land Development Plan and
issuance of any required permits.
1. In response to questioning from Patty
Estheimer, Mr. Van Blargan admitted that there would be some impact on the
southern wetland areas by filling in the middle area which would disrupt the
functionality of the adjoining wetland areas.
However, he testified that because the wetlands are of such low quality
the mitigated areas may actually be an improvement to the overall wetland
quality on the property.
2. Notice of the public hearing held on
March 14, 2002 was properly advertised, notice was posted at the municipal
building, the subject property was properly posted and all adjoining property
owners were notified by certified mail.
3.
CONCLUSIONS
1. Section 195-72.(B)(2)(b) permits
utilities and public facilities and improvements, such as streets, in the
floodplain district so long as the requirements of Section 195-77 of the Zoning
Ordinance with regard to special exceptions and floodplain districts are
addressed and satisfied.
2. The twelve factors set forth at
195-77.A. of the Zoning Ordinance were addressed by Applicant and those factors
and Applicant’s document demonstrating satisfaction thereof are incorporated
herein by reference.
3. Accordingly, the requirements for
permitting the special exception for the realignment of Piketown Road within
the floodplain have been satisfied.
4. Applicant needs a variance from certain
provisions of the Zoning Ordinance in order to complete its project which
includes construction activities within the three of the environmental
protection overlay districts.
5. Specifically, Section 195-79(C) of the
Zoning Ordinance does not permit the proposed uses within the SPOD; Section
195-80(B) does not permit the proposed uses within the HSPOD; and Section
195-82(C) does not permit the proposed uses within the WPOD.
6. Section 195-199 of the Zoning Ordinance
and Section 910.2 of the Pennsylvania Municipalities Planning Code allow the
Zoning Hearing Board to act on requests for variances and to grant such
requests under certain conditions of hardship and may attach such reasonable
conditions and safeguards as it may deem necessary to implement the purposes of
the Zoning Ordinance.
7. There are unique physical circumstances
or conditions of the subject property, including exceptional topographical and
physical conditions of the property along Beaver Creek, and the presence of
many environmental protection overlay districts which interfere with the ability
to utilize the property as a public high school campus as permitted by the
conditional use approval granted by the Township.
8. The unique physical circumstances or
conditions of the subject property have not been created by the Applicant.
9. Variance from the limitations and uses
within the environmental protection overlay districts, if approved, would not
alter the essential character of the neighborhood or district in which the
property is located nor substantially or permanently impair the appropriate use
or development of adjacent property nor be detrimental to the public welfare.
10. The variance from the environmental
protection overlay district restrictions, subject to the conditions hereinafter
set forth as agreed to by Applicant, will represent the minimum variance that
will afford relief and represent the least modification possible for the
regulations in issue.
11. With regard to the requested variances
from the restrictions of the environmental protection overlay districts, the
quantum of proof required to establish an unnecessary hardship is less than in
a use variance case in accordance with the holding of Talkish v. Zoning
Hearing Board of Harborcreek Township.
12. Under the holding of that case, when
evaluating the unnecessary hardship with regard to a dimensional variance
involving only a reasonable adjustment of open areas and open space
requirements, the Zoning Hearing Board may consider multiple factors including
economic detriment if the variance is denied, characteristics of the surrounding
neighborhood and other applicable factors.
13. Approximately one-fourth of the WPOD
acreage is impacted by the project.
14. Only a little over one-fifth of the
identified wetlands are impacted and of those, a large portion of the acreage
is wetlands of low quality.
15.
There are four areas of HSPOD lands,
most of which are impacted. However,
Applicant agreed to the specific condition that those areas be regraded in such
a way that erosion will be eliminated.
16. Approval of the request for a special
exception to permit construction and realignment of Piketown Road and grant of
the requested variances would be subject to the reasonable conditions
specifically agreed to by Applicant, as stated above under the Findings of
Fact.
DECISION
In
view of the foregoing findings and conclusions, and in view of the evidence and
testimony presented to the Zoning Hearing Board, it is the Decision of the
Board that the requested special exception and variances from the limitations
of the environmental protection overlay districts contained in Section
195-79(C), 195-80(B), and 195-82(C) of the Zoning Ordinance are hereby GRANTED,
subject to the following conditions:
(1) Applicant
shall provide one to one onsite wetlands mitigation of officially delineated wetland
areas adjacent to existing wetlands;
(2) There will be no increase in the flood
height of Beaver Creek;
(3) There will be no increase in the flood
velocity of Beaver Creek;
(4) Any disturbed HSPOD areas will be leveled
and not permitted to erode; and
(5) Approval of a Land Development Plan and
issuance of any required permits.
[BOARD MEMBER SIGNATURES FOLLOW ON
PAGE 12]
DATE: WEST
HANOVER TOWNSHIP ZONING HEARING BOARD
Brian
F. Jacobeen, Chairman
Ruth
C. Shields
Norma
J. Gruber
Neil
Shatto
DISSENT:
Linda L. Turns